Question 4: (4 Marks)
Activity Depend On Duration
C — 6
A — 7
B — 8
D A & B 9
G C 6
E C 5
H B & C 7
F E & H 10
Given a small project as shown in table:
It is required to:
• Draw (PDM) network;
• Calculate activity times;
• Find project duration;
• Locate critical path;
• Find total float of each activity;
• Find free float of each activity;
• Convert to (ADM) network.
Sample Solution