Capital Investment, Inc. (CI)

Capital Investment, Inc. (CI) is a small investment banking firm specializing in securing funds for small- to
medium-sized technology firms. CI uses a standardized project format for each client engagement. The
only items that need to be changed in the standard network of activities are the duration of activities
(activity times) and to occasionally add any unusual circumstances for the client engagement.
MaryBeth Simms is assigned to the XYZ Company as a project manager partner. She has compiled the
following information and activity time for XYZ Company.
Activity Description Immediate
Predecessor(s)
Time in Workdays
Optimistic Likely Pessimistic
A
Begin draft contract using
template -- 4 7 10
B Research client firm -- 2 4 8
C
Create “due diligence”
rough draft A, B 2 5 8
D
Coordinate proposal with
client needs C 16 19 28
E
Estimate future demand
and cash flows C 6 9 24
F
Draft plans for client
company future growth E 1 7 13
G
Create and approve legal
documents C 4 10 28
H
Combine all drafts into
“first-draft” client proposal D, F, G 2 5 14
I
Secure potential sources of
capital G, F 5 8 17
J
Check and approve final
legal proposal H 2 5 8
K
Sign contract and transfer
funds to client I, J 17 29 45
Discussion and Report to Management
Simms and the other partners at CI have a policy of reviewing the plans with a project review committee.
The committee checks that all details are covered, times are realistic, and resources are available. Simms
asks you to generate a report that includes a planned schedule and expected project completion time in
days. You will need to include a project network diagram in your report.
Note that the average duration to source a capital project with 70 workdays. CI partners have agreed to
a best practice of setting up projects with a 90% chance of hitting the plan.

  1. How does the project for XYZ align with an average project?
  2. What average would be necessary to ensure a 95% chance of completing the project in 70 days?

Sample Solution