Project Summary - Answer the following questions:
You are the project manager of a project to build vegetable gardens for a non profit that supplies healthy
food to community shelters.
You are to build two gardens a month for 12 months.
Each garden is planned to cost $100.
Your project is scheduled to last for 12 months.
It is the beginning of month 10.
You have built 20 vegetable gardens and your CPI is .9091.

  1. How is the project performing?
    A. Over budget and ahead of schedule
    B. Under budget and ahead of schedule
    C. Over budget and behind schedule
    D. Under budget and behind schedule.
  2. How dis you come to your conclusion ?
  3. How can this information be valuable to a non profit with such a mission?
  4. How can this information be valuable to the project manager?