Order releasing, dispatching, and progress reporting are the three primary functions of Production Activity Control (PAC). To accomplish the plans, PAC must establish detailed schedules for each order, set priorities for work to be done at each work center, and keep them current.

Describe forward and backward scheduling at this implementation phase and why backward scheduling is preferred?

Sample Solution

Forward scheduling is a technique used to plan the production activities of an order from the initial release date. This entails starting with the original due date and working backwards to each preceding step in the process until all planned activities for the order have been determined.