Project Management

  1. By using the data provided in Table 1, Find the project duration after constructing the network diagram.
  2. According to the project data, only 8 cranes are available for the work and each activity has to be completed without break. Manually allocate resources and find the minimum project duration (for crane resource only and neglect others). Also, identify in details the main problems associated with resources.
  3. Calculate BCWS, BCWP, ACWP, CV, and SV for the project manually, comment on the progress of the project.
  4. Evaluate cost and schedule performance ratios for materials and excavator only. Comment on progress of the contract.
  5. Calculate the total cost per hour for the excavator which is powered by a 200-hp engine based on the data provided in Table 3.
  6. Assume that a Team of workers can install X square yards of carpeting in Y hours. If the number of workers and man-hours stay the same but the output (Productivity) increases by P%, find the number square yards installs after the increase in productivity? (Use Table 4)
  7. Discuss the reasons behind and the effect of lowering of crews’ production rate along with the suggested procedure to improve the production rate.