Tegdiws and Widgets for use in its production system

Order Description Jill’s Job Shop buys two parts (Tegdiws and Widgets) for use in" rel="nofollow">in its production system from two different suppliers. The parts are needed throughout the entire 50- week year, Tegdiws are used at a relatively constant rate and are ordered whenever the remain" rel="nofollow">inin" rel="nofollow">ing quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every three weeks. Data for both products are as follows: ITEM TEGDIW WIDGET Annual demand 10,000 5,000 Holdin" rel="nofollow">ing cost (% of item cost) 20% 20% Setup or order cost $150,000 $25.00 Lead time 4 weeks 1 week Safety stock 55 units 5 units Item cost $10.00 $2.00 a. What is the in" rel="nofollow">inventory control system for Tegdiws? That is, what is the reorder quantity and what is the reorder poin" rel="nofollow">int? b. What is the in" rel="nofollow">inventory control system for Widgets?